900 KLD Sewage Treatment Plant — ASP & MBBR Options
Page Summary
This page provides two complete options for a 900 KLD (900 m³/day) sewage treatment plant: ASP (Activated Sludge Process) and MBBR (Moving Bed Biofilm Reactor). Default design assumptions: 20 operating hours/day, influent BOD₅ assumed = 250 mg/L. All calculations shown digit-by-digit. Final design & guarantees after site survey and influent lab report.
Design Basis — Common Inputs
- Plant capacity Qday = 900 m³/day (900 KLD).
- Operating hours = 20 hr/day.
- Assumed influent BOD₅ = 250 mg/L (confirm with lab).
- Oxygen requirement factor = 1.4 kg O₂ / kg BOD.
- Clarifier SOR = 30 m³/m²·day.
- Sludge yield = 0.5 kg DS / kg BOD.
General hydraulic calculations (digit-by-digit)
Qhr = Qday ÷ operating_hours = 900 ÷ 20 = 45.0 m³/hr.
Qhr in litres per hour = 45.0 × 1000 = 45,000 LPH.
BOD load/day = Qday × Influent_BOD ÷ 1000 = 900 × 250 ÷ 1000 = 225.0 kg BOD/day.
O₂ required/day = BOD_load × 1.4 = 225.0 × 1.4 = 315.0 kg O₂/day.
Option A — 900 KLD STP — ASP (Activated Sludge Process)
ASP is a continuous suspended-growth biological system — proven for large, stable flows where trained operation is available.
ASP Design Calculations (digit-by-digit)
Assume Aeration HRT = 6 hours.
Working volume Vaer = Qhr × HRT = 45.0 × 6 = 270.0 m³ (working).
Add 15% freeboard → physical volume ≈ 270.0 × 1.15 = 310.50 m³.
MLSS = 3,000 mg/L = 3.0 kg/m³. Biomass mass = MLSS × V_working = 3.0 × 270.0 = 810.0 kg suspended solids.
SOR = 30 m³/m²·day → Area A = Qday ÷ SOR = 900 ÷ 30 = 30.0 m².
Choose circular clarifier diameter d: d = √(4A/π) = √(120 ÷ π) ≈ √(38.197) = 6.18 m. Choose practical diameter ≈ 6.2 m (or provide multiple modules).
Sludge DS/day = BOD_load × yield = 225.0 × 0.5 = 112.5 kg DS/day.
At 3% cake solids → wet sludge ≈ 112.5 ÷ 0.03 = 3,750 L/day.
O₂ req/day = 315.0 kg O₂/day. Using 1.2 kg O₂ per kW practical allowance → blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW. Recommend distributed blowers (for example: 6 × 50 kW or 4 × 75 kW with redundancy and VFD control) sized after detailed oxygen transfer and DO setpoints are confirmed.
ASP Process Flow (text)
ASP Main Equipment & Scope
- Mechanical bar screens & grit removal
- Collection / equalization tank with mixers
- Aeration tank (270 m³ working / 310.5 m³ physical) with fine-bubble diffusers
- Blowers: total indicative ~262.5 kW (split duty + standby), DO control, silencers & VFD
- Secondary clarifier (Ø ~6.2 m) with hopper & RAS pumps
- Polishing train: Pressure Sand Filter, Activated Carbon Filter, UF/Cartridge options
- Hypochlorite dosing skid for disinfection
- Sludge handling: sump, sludge pump, dewatering (belt press/drying beds)
- PLC control panel, instrumentation (DO, level, flow)
ASP MOC & Notes
- Tank MOC: RCC / MSEP / FRP with rubber lining (as per site & budget)
- Piping: HDPE/UPVC for process; SS304 for critical wetted parts if required
- Electrical: MCC, backup generator provision recommended for continuous operation
Option B — 900 KLD STP — MBBR (Moving Bed Biofilm Reactor)
MBBR uses floating carriers to develop biofilm — compact, robust to shock loads, lower suspended sludge yield and often smaller footprint.
MBBR Design Calculations (digit-by-digit)
Assume MBBR HRT = 4 hours.
V_working = Qhr × HRT = 45.0 × 4 = 180.0 m³ working.
Add 15% freeboard → physical volume ≈ 180.0 × 1.15 = 207.0 m³.
Media fill fraction = 50% (typical) → media volume = 180.0 × 0.50 = 90.0 m³ of carriers (e.g., Kaldnes type).
Use same clarifier SOR: A = 900 ÷ 30 = 30.0 m². Circular dia ≈ 6.2 m (same as ASP) or multiple smaller modules as preferred.
4) Sludge estimate
MBBR has lower sludge yield; choose conservative yield = 0.4 kg DS/kg BOD → DS/day = 225.0 × 0.4 = 90.0 kg DS/day.
At 3% cake solids → wet sludge ≈ 90.0 ÷ 0.03 = 3,000 L/day.
O₂ req/day = 315.0 kg O₂/day (same BOD load). Use oxygen transfer efficiency & mixing allowance; using 1.2 kg O₂/kW → blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW (indicative). MBBR may require slightly more mixing energy — design with vendor ATS and pilot tests.
MBBR Process Flow (text)
MBBR Main Equipment & Scope
- Equalization tank & transfer pumps
- MBBR reactor (180 m³ working / 207 m³ physical) with ~90 m³ carriers
- Fine bubble diffusers & blowers (~262.5 kW indicative) with VFD
- Media retention screens, secondary clarifier (Ø ~6.2 m)
- Polishing: PSF, ACF, UF options
- Hypochlorite dosing & PLC controls
MBBR MOC & Notes
- Reactors: RCC / MSEP / FRP with rubber lining
- Carriers: HDPE proven vendor media; retention screens & sample ports mandatory
- Retrofit-friendly: MBBR can be installed into existing tanks to save civil cost
ASP vs MBBR — Quick Comparison (900 KLD)
| Feature | ASP | MBBR |
|---|---|---|
| Footprint | Moderate (aeration + clarifier) | Smaller (higher surface area with carriers) |
| Sludge yield | Higher (~112.5 kg DS/day) | Lower (~90.0 kg DS/day) |
| Operator skill | Requires trained operators | Less operator-intensive, more robust |
| Retrofit | Possible with modifications | Excellent for retrofit (drop-in carriers) |
| Capital cost | Lower equipment cost, more civil | Higher media cost, lower civil |
Operation & Maintenance — Common
- Daily: Check screens, pumps, blowers, DO (target 2–3 mg/L in aeration/reactor), sludge blanket, alarms
- Weekly: Inspect diffusers, remove ragging, backwash polishing filters
- Monthly: Calibrate DO & level sensors, inspect blower filters & motors
- Periodic: Sludge dewatering, media inspection (MBBR), diffuser replacement, CIP if needed
- We offer operator training, spare parts & AMC packages for large STPs
Common Issues & Troubleshooting
- Low DO: Check blower runs, VFD settings, diffuser clogging.
- Clarifier solids passing: Adjust RAS, check sludge return, inspect SRT/MLSS balance.
- Foaming: Identify surfactant source; dose anti-foam and control SRT/MLSS.
- Media loss (MBBR): Verify outlet screens and repair media retention pockets.
FAQ — 900 KLD STP
Q: Which option is better — ASP or MBBR for 900 KLD?
Answer: Both work. Choose ASP when you have trained operators and want lower media costs; choose MBBR for smaller footprint, robustness to shock loads and easier retrofit. We help you choose after site & influent analysis.
Q: What raw data is required for final design?
Answer: Raw influent lab report — BOD, COD, TSS, TDS, FOG, pH, temperature — plus site levels, power availability and reuse/discharge requirements.
Q: Can you provide performance guarantees?
Answer: Yes — after site survey, agreed influent, and signed scope we provide performance guarantees & AMC options.