900 KLD Sewage Treatment Plant — ASP & MBBR | RRR ENVIRO SYSTEMS

900 KLD Sewage Treatment Plant — ASP & MBBR Options

Turnkey 900 KLD STP — choose Activated Sludge Process (ASP) or MBBR technology. Full design, civil + mech + electrical, commissioning & AMC. ISO 9001:2015 — RRR ENVIRO SYSTEMS.

Page Summary

This page provides two complete options for a 900 KLD (900 m³/day) sewage treatment plant: ASP (Activated Sludge Process) and MBBR (Moving Bed Biofilm Reactor). Default design assumptions: 20 operating hours/day, influent BOD₅ assumed = 250 mg/L. All calculations shown digit-by-digit. Final design & guarantees after site survey and influent lab report.

Design Basis — Common Inputs

  • Plant capacity Qday = 900 m³/day (900 KLD).
  • Operating hours = 20 hr/day.
  • Assumed influent BOD₅ = 250 mg/L (confirm with lab).
  • Oxygen requirement factor = 1.4 kg O₂ / kg BOD.
  • Clarifier SOR = 30 m³/m²·day.
  • Sludge yield = 0.5 kg DS / kg BOD.

General hydraulic calculations (digit-by-digit)

1) Hourly flow
Qhr = Qday ÷ operating_hours = 900 ÷ 20 = 45.0 m³/hr.
Qhr in litres per hour = 45.0 × 1000 = 45,000 LPH.
Q_hr = 900 ÷ 20 = 45.0 m³/hr Q_hr_LPH = 45.0 × 1000 = 45,000 LPH
2) BOD load
BOD load/day = Qday × Influent_BOD ÷ 1000 = 900 × 250 ÷ 1000 = 225.0 kg BOD/day.
BOD_load = 900 × 250 ÷ 1000 = 225.0 kg/day
3) Oxygen requirement
O₂ required/day = BOD_load × 1.4 = 225.0 × 1.4 = 315.0 kg O₂/day.
O2_req = 225.0 × 1.4 = 315.0 kg/day

Option A — 900 KLD STP — ASP (Activated Sludge Process)

ASP is a continuous suspended-growth biological system — proven for large, stable flows where trained operation is available.

ASP Design Calculations (digit-by-digit)

4) Aeration tank volume (HRT method)
Assume Aeration HRT = 6 hours.
Working volume Vaer = Qhr × HRT = 45.0 × 6 = 270.0 m³ (working).
Add 15% freeboard → physical volume ≈ 270.0 × 1.15 = 310.50 m³.
V_aer = 45.0 × 6 = 270.0 m³ V_physical ≈ 270.0 × 1.15 = 310.50 m³
5) MLSS & biomass
MLSS = 3,000 mg/L = 3.0 kg/m³. Biomass mass = MLSS × V_working = 3.0 × 270.0 = 810.0 kg suspended solids.
Biomass = 3.0 × 270.0 = 810.0 kg
6) Clarifier sizing
SOR = 30 m³/m²·day → Area A = Qday ÷ SOR = 900 ÷ 30 = 30.0 m².
Choose circular clarifier diameter d: d = √(4A/π) = √(120 ÷ π) ≈ √(38.197) = 6.18 m. Choose practical diameter ≈ 6.2 m (or provide multiple modules).
A = 900 ÷ 30 = 30.0 m² d ≈ sqrt(4×30 ÷ π) ≈ 6.18 m → choose 6.2 m
7) Sludge estimate
Sludge DS/day = BOD_load × yield = 225.0 × 0.5 = 112.5 kg DS/day.
At 3% cake solids → wet sludge ≈ 112.5 ÷ 0.03 = 3,750 L/day.
DS/day = 225.0 × 0.5 = 112.5 kg Wet_sludge ≈ 112.5 ÷ 0.03 = 3,750 L/day
8) Blower sizing (indicative)
O₂ req/day = 315.0 kg O₂/day. Using 1.2 kg O₂ per kW practical allowance → blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW. Recommend distributed blowers (for example: 6 × 50 kW or 4 × 75 kW with redundancy and VFD control) sized after detailed oxygen transfer and DO setpoints are confirmed.
Blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW (indicative)

ASP Process Flow (text)

Inlet → Bar Screen → Oil & Grease Trap → Grit Chamber → Collection/Equalization Tank (with mixer) → Raw Sewage Transfer Pumps → Aeration Tank (ASP) with diffusers → Secondary Clarifier → Polishing (PSF/ACF/UF if required) → Disinfection → Treated Water Tank → Reuse/Discharge. Sludge: Sludge sump → Thickening → Dewatering → Disposal.

ASP Main Equipment & Scope

  • Mechanical bar screens & grit removal
  • Collection / equalization tank with mixers
  • Aeration tank (270 m³ working / 310.5 m³ physical) with fine-bubble diffusers
  • Blowers: total indicative ~262.5 kW (split duty + standby), DO control, silencers & VFD
  • Secondary clarifier (Ø ~6.2 m) with hopper & RAS pumps
  • Polishing train: Pressure Sand Filter, Activated Carbon Filter, UF/Cartridge options
  • Hypochlorite dosing skid for disinfection
  • Sludge handling: sump, sludge pump, dewatering (belt press/drying beds)
  • PLC control panel, instrumentation (DO, level, flow)

ASP MOC & Notes

  • Tank MOC: RCC / MSEP / FRP with rubber lining (as per site & budget)
  • Piping: HDPE/UPVC for process; SS304 for critical wetted parts if required
  • Electrical: MCC, backup generator provision recommended for continuous operation

Option B — 900 KLD STP — MBBR (Moving Bed Biofilm Reactor)

MBBR uses floating carriers to develop biofilm — compact, robust to shock loads, lower suspended sludge yield and often smaller footprint.

MBBR Design Calculations (digit-by-digit)

1) Aeration/reactor volume (HRT method)
Assume MBBR HRT = 4 hours.
V_working = Qhr × HRT = 45.0 × 4 = 180.0 m³ working.
Add 15% freeboard → physical volume ≈ 180.0 × 1.15 = 207.0 m³.
V_MBBR = 45.0 × 4 = 180.0 m³ V_physical ≈ 180.0 × 1.15 = 207.0 m³
2) Carrier media volume
Media fill fraction = 50% (typical) → media volume = 180.0 × 0.50 = 90.0 m³ of carriers (e.g., Kaldnes type).
V_media = 180.0 × 0.50 = 90.0 m³
3) Clarifier sizing
Use same clarifier SOR: A = 900 ÷ 30 = 30.0 m². Circular dia ≈ 6.2 m (same as ASP) or multiple smaller modules as preferred.
4) Sludge estimate
MBBR has lower sludge yield; choose conservative yield = 0.4 kg DS/kg BOD → DS/day = 225.0 × 0.4 = 90.0 kg DS/day.
At 3% cake solids → wet sludge ≈ 90.0 ÷ 0.03 = 3,000 L/day.
DS/day = 225.0 × 0.4 = 90.0 kg Wet_sludge ≈ 90.0 ÷ 0.03 = 3,000 L/day
5) Oxygen & blower sizing (indicative)
O₂ req/day = 315.0 kg O₂/day (same BOD load). Use oxygen transfer efficiency & mixing allowance; using 1.2 kg O₂/kW → blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW (indicative). MBBR may require slightly more mixing energy — design with vendor ATS and pilot tests.
Blower_kW ≈ 315.0 ÷ 1.2 = 262.5 kW (indicative)

MBBR Process Flow (text)

Inlet → Bar Screen → Oil & Grease Trap → Grit → Equalization Tank → Raw Sewage Transfer Pumps → MBBR Reactor (aeration + carriers) → Secondary Clarifier → Polishing (PSF/ACF/UF) → Disinfection → Treated Water Tank → Reuse/Discharge. Provide media retention screens at outlets and media handling plan.

MBBR Main Equipment & Scope

  • Equalization tank & transfer pumps
  • MBBR reactor (180 m³ working / 207 m³ physical) with ~90 m³ carriers
  • Fine bubble diffusers & blowers (~262.5 kW indicative) with VFD
  • Media retention screens, secondary clarifier (Ø ~6.2 m)
  • Polishing: PSF, ACF, UF options
  • Hypochlorite dosing & PLC controls

MBBR MOC & Notes

  • Reactors: RCC / MSEP / FRP with rubber lining
  • Carriers: HDPE proven vendor media; retention screens & sample ports mandatory
  • Retrofit-friendly: MBBR can be installed into existing tanks to save civil cost

ASP vs MBBR — Quick Comparison (900 KLD)

FeatureASPMBBR
FootprintModerate (aeration + clarifier)Smaller (higher surface area with carriers)
Sludge yieldHigher (~112.5 kg DS/day)Lower (~90.0 kg DS/day)
Operator skillRequires trained operatorsLess operator-intensive, more robust
RetrofitPossible with modificationsExcellent for retrofit (drop-in carriers)
Capital costLower equipment cost, more civilHigher media cost, lower civil

Operation & Maintenance — Common

  • Daily: Check screens, pumps, blowers, DO (target 2–3 mg/L in aeration/reactor), sludge blanket, alarms
  • Weekly: Inspect diffusers, remove ragging, backwash polishing filters
  • Monthly: Calibrate DO & level sensors, inspect blower filters & motors
  • Periodic: Sludge dewatering, media inspection (MBBR), diffuser replacement, CIP if needed
  • We offer operator training, spare parts & AMC packages for large STPs

Common Issues & Troubleshooting

  • Low DO: Check blower runs, VFD settings, diffuser clogging.
  • Clarifier solids passing: Adjust RAS, check sludge return, inspect SRT/MLSS balance.
  • Foaming: Identify surfactant source; dose anti-foam and control SRT/MLSS.
  • Media loss (MBBR): Verify outlet screens and repair media retention pockets.

FAQ — 900 KLD STP

Q: Which option is better — ASP or MBBR for 900 KLD?

Answer: Both work. Choose ASP when you have trained operators and want lower media costs; choose MBBR for smaller footprint, robustness to shock loads and easier retrofit. We help you choose after site & influent analysis.

Q: What raw data is required for final design?

Answer: Raw influent lab report — BOD, COD, TSS, TDS, FOG, pH, temperature — plus site levels, power availability and reuse/discharge requirements.

Q: Can you provide performance guarantees?

Answer: Yes — after site survey, agreed influent, and signed scope we provide performance guarantees & AMC options.

RRR ENVIRO SYSTEMS · 900 KLD STP (ASP / MBBR) · Est. 2011 · ISO 9001:2015

Contact: +91 97100 35249 • +91 99623 95875 • rrrenviro@gmail.com